PHUPHAtara

The construction work of condominium tower A,B
and villa house has been running smoothly according
to the plan. more
detail
• Condominium
Tower A’s structural work of the 1st- 4th
Floor have been finished,
the 5th Floor is 80%, the 6th Floor is 20%, brick work of the 1st Floor is
60%, lift core is 40% completed.
Tower B’s structural work of the 1st,3rd,4th,5th,6th
Floor have completed,
the 2nd Floor is 65%, the 7th Floor is 80%, lift core is 50% completed.
• Villa
Type A # 9 trusses is 90%, wall work is 10%, plaster work is 95%, electronically
conduit & sanitary piles are 20% completed.
Type A # 12 wall work is already finish, plaster
work is 95%, electronically conduit & sanitary
piles are
95%, ceiling is 70%, door and window frame are 80% completed.