Boathouse Hua Hin

The construction work of condominium B,C and
their facilities has been running smoothly according
to the plan.
• Condominium
B
Tower B’s structural work and piling
work are 100% completed, foundation work for
main building is 50% completed.
• Condominium
C
Tower C’s structural work is 100% completed,
architectural work is 90%, electrical is 88%
completed, plumbing work is 97% completed, HVAC
(Heating, Ventilating, and Air-Conditioning)
is 95% completed and ceramic tiling work for
the front swimming pool is 15% completed.
• Facilities
The “Lighthouse” clubhouse and
the “clubhouse” multi-function building
are 100% finished and already in service, the
Beachfront Park is 100% completed. The featured
Park’s structural and architectural works
are 100% completed. The landscape is more than
50% completed.